2018亚洲天天射,澳门黄色电影免费三级大毛片,337p欧洲大胆艺术,男人天堂色男人色天堂,三级黄色网站,91亚洲欧美,亚洲欧美日本另类激情

Chinese-built power plants in Uganda to reduce tariff rate by 17.5 pct

Source: Xinhua| 2019-05-15 22:33:09|Editor: ZX
Video PlayerClose

KAMPALA, May 15 (Xinhua) -- The Ugandan government said here Wednesday that Chinese-constructed Isimba and Karuma hydro power plants will reduce the generation tariff in the east African country by 17.45 percent.

Once the two power plants are commissioned and the power fully utilized, the generation tariff will reduce from the current 6.47 U.S. cents/kWh to 5.34 cents/kWh, said a statement of Uganda's ministry of energy and mineral development.

The 183MW Isimba Hydro Power Plant was commissioned in March while the 600MW Karuma Hydro Power Plant is under construction.

Uganda currently has a total installed generation capacity of 1,202MW, according to the ministry figures.

TOP STORIES
EDITOR’S CHOICE
MOST VIEWED
EXPLORE XINHUANET
010020070750000000000000011100001380612771